P-1001
Formal Bid
Expired
Whole-home repipe — Anderson
Customer
Anderson Residence
Job #
J-1001
Assigned Technician
Mike Reyes
Type
Formal Bid
Date Issued
Dec 28, 1969
Approval Deadline
Jan 11, 1970
Total Estimated Cost
$5,685.00
Worksheet — Cost Breakdown
| Description | Category | Qty | Unit Cost | Markup % | Total |
|---|---|---|---|---|---|
| Repipe labor | Labor | 32 | $95.00 | — | $3,040.00 |
| PEX-A tubing & fittings | Material | 1 | $1,850.00 | 20% | $2,220.00 |
| Permit & inspection | Other | 1 | $425.00 | — | $425.00 |
Subtotal$5,315.00
Markup$370.00
Grand Total$5,685.00
Proposal Details
Scope of Work
Replace all hot/cold supply lines from main shutoff through every fixture with PEX-A. Includes pressure test, drywall openings, and inspection.
Exclusions
Drywall repair and paint not included.
Assumptions
Attic access available; no asbestos abatement required.
Warranty Information
10-year manufacturer warranty on PEX; 2-year labor warranty.
Payment Terms
50% deposit on signing, balance on completion.
Document Attachments
| File Name | Type | Uploaded By | Date | |
|---|---|---|---|---|
| site-photo-utility-room.jpg | Photo | Mike Reyes | Dec 27, 1969 |
Signature & Approval
Send the proposal to collect a customer signature.
Internal Notes
Customer asked for mid-week start.
Sarah Kim · Dec 29, 1969